jobs remaining at a particular point in time. The jobs are labeled A, B, C, D, and E in
the order that they entered the shop. The respective processing times and due dates are
given in the table below. is the sequence the of jobs by CR rules?
Job
Processing Time
Due Date
A
29
32
B.
2
55
11
34
D
31
60
33
35