1. The project is estimated to be completed 1/8/2016. It will take approximately 260 days 2. The critical path for this project follows: 1.1, 1.2, 1.3, 1.4, 1.7, 1.8, 1.10,

1. The project is estimated to be completed 1/8/2016. It will take approximately 260 days
2. The critical path for this project follows: 1.1, 1.2, 1.3, 1.4, 1.7, 1.8, 1.10, 1.11, 1.12, 1.14,
1.15, 1.16
3. The greatest slack exists in task 1.5, Detailed Marketing Plan 179 days
4. There exists only one critical Path, so it is not a very sensitive network
5. The two project milestones are:
1.8 Build Prototypes, because this allows you to build and test the product prototypes,
and determine if the product meets the specifications or needs to be reworked.
1.11 Finalized Project Designs, because this confirms the product meets specification,
and is able to be manufactured. i need explanation on question 1 to 5, how it was calculated

Do you need us to help you on this or any other assignment?


Make an Order Now
0 replies

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *