Could you to solve it. For B i couldn’t know what’s wrong i did The product structure. Bracket Spring (1) Base (1) Clamp(4) Housing(1) Clamp(2) Casting(2) Bearing (1) Shaft 2)

Could you to solve it. For B i couldn’t know what’s wrong i did The product structure.
Bracket
Spring (1)
Base (1)
Clamp(4)
Housing(1)
Clamp(2)
Casting(2)
Bearing (1)
Shaft 2)
Handle
Handley
Casting(2) b) Determine the gross quantities needed of each item if you are to assemble 100 brackets.
Click the icon to view the completed product structure.
Base:
100
units (enter your response as a whole number).
Spring:
100
units (enter your response as a whole number).
Clamp:
600
units (enter your response as a whole number).
Housing:
100
units (enter your response as a whole number).
Handle:
100
units (enter your response as a whole number).
Casting:
400
units (enter your response as a whole number).
Bearing:
100
units (enter your response as a whole number).
Shaft:
200
units (enter your response as a whole number). As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 1 spring, and 4 clamps. The base is assembled from 2 clamps and 1 housing.
Each clamp has 1 handle and 2 castings. Each housing has 1 bearing and 2 shafts. There is no inventory on hand.
a) Design a product structure noting the quantities for each item and show the low-level coding. Match each number in the structure below with the corresponding item.
Bracket
Number
Item
Spring(1)
Housing(1)
Base(1)
Casting(2)
IV
Shaft(2)
Clamp(4)
II
Clamp(2)
Bearing(1)
IV
Handle(1)
Casting(2)
Handle(1)
III

Do you need us to help you on this or any other assignment?