You have been hired by lnnovative Solutions to plan the development of a web site for Sydney Flowers (SF). They have decided to set it up on a local server

You have been hired by lnnovative Solutions to plan the development of a web site for Sydney Flowers (SF). They have decided to set it up on a local server and some of the test team need operational training. You have identified the major task headings, durations and dependencies as shown in the table below. Everyone will be working 5-day weeks. a. Draw a network diagram showing all the tasks and their dependencies (abbreviate their names if necessary). Arrange the tasks to achieve the shortest time to complete the project and determine the number of weeks it will take to complete the project. b. Calculate the slack or float time for each activity, on the understanding that many tasks can be run in parallel if dependencies permit c. Finally, list the task numbers that form the critical path. Task Duration Depends On A. Proposal sign—off 0 days B. Detailed Requirement Analysis 3 days A
C. Hardware and Software analysis 1dav B
D. Develop Website 10 davs B
E. Acquire and setup Hardware and Software 5 days (I
F. Server Administrator trained 3 days I3
G. Web svstem loaded onto server 3 days D, E
H. Test Website 1 day 6
|. Evaluate Training requirements 4 days F, H
J. Develop Training documents 3 days |
K. Database created on server 5 days E, H
L. Test Database 1 day K
M. Train KF employees 4 days J, L
N. Data Migration 5 days L. M
0. User Acceptance Testing 2 days F, N
P. Approval to go live 0 days CI

Do you need us to help you on this or any other assignment?


Make an Order Now
0 replies

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *