When you have completed the bulk of the planning on your project, it is time to strike a baseline. Although the baseline can be created in the Gantt chart view

When you have completed the bulk of the planning on your project, it is time to strike a baseline.  Although the baseline can be created in the Gantt chart view it is more practical to use the _____________________ view.  Before striking the baseline you should display the ____________________ table.  This table contains the Task Name, Start, Finish, Baseline Start, Baseline Finish, Start Variance, and Finish Variance fields. A. Task Usage view, Schedule Table B. Tracking Gantt view, Schedule Table C. Tracking Gantt view, Variance Table D. Task Usage view, Variance Table